DECOMP PDT members,
The Interagency Modeling Center (IMC) has completed the SFWMM preliminary
screening of the DECOMP "conceptual alternatives" / backfill options. Scope
details for this screening analysis have been previously provided during the
March and June 2009 DECOMP PDT meetings, and a concise overview is provided
in this email.
Included as part of this SFWMM screening analysis are the following five
"conceptual alternatives":
(1) 2015 Future Without Project Baseline (no backfill);
(2) Complete backfill on the Miami Canal (MC) segment under consideration for
PIR 1 (S-8 to S-151);
(3) Complete backfill of the north MC segment (S-8 to S-339);
(4) Complete backfill of the central MC segment (S-339 to S-340);
(5) Complete backfill of the south MC segment (S-340 to S-151).
As a component of the DECOMP Modeling Strategy, the SFWMM Preliminary
Screening is envisioned to assist in finalizing details of the final array of
alternatives and potential elimination of management measures from further
consideration.